Work Session E, Friday August 2, 2013 #2

Discussion Pertaining to Work Session E - 2013

Work Session E, Friday August 2, 2013 #2

Unread postby Joe Kanocz » Fri Aug 02, 2013 7:12 pm

Progress continues on the RPO. The wall that divides the mail and baggage/freight area is done. The frieght/baggage compartment is done other than final paint/finishing.
20130802_130157.jpg

20130802_130205.jpg

On the mail side, a wall for the bathroom/toilet is being installed. Guess where the toilet drained????? :eek:
20130802_130245.jpg

Up on the snow shed, the final touches were done. Not only was a massive beam replaced, but a lot of metal flashing was installed to protect the other wood.
DSC00288.JPG

The snow shed with a moon roof. All of these boards were removed to install metal flashing for water/moisture protection.
20130801_164633.jpg
Joe Kanocz
Moderator
Moderator
 
Posts: 580
Joined: Thu Nov 17, 2011 5:06 pm

Re: Work Session E, Friday August 2, 2013 #2

Unread postby John Cole » Sun Aug 04, 2013 7:44 am

Good to be home after a 15 hour drive. Craig McMullen joked that we should put Lexan plastic in the gaps and call them skylights. :-) Considering that we opened up nine of them, that would be ALOT of plastic...
John Cole
Conductor
Conductor
 
Posts: 729
Joined: Mon Nov 28, 2011 12:55 pm

Re: Work Session E, Friday August 2, 2013 #2

Unread postby John Cole » Mon Aug 05, 2013 10:09 am

I talked Ed Bodette and he assured me that all of our nice cover of tin will have a protective coating on exhaust soot on them in just a few weeks. :-)
John Cole
Conductor
Conductor
 
Posts: 729
Joined: Mon Nov 28, 2011 12:55 pm


Return to Work Session E (July 29 - August 2)

Who is online

Users browsing this forum: No registered users and 2 guests