Page 1 of 1

WORK SESSION D - Friday, July 28, 2013 - Part II

Unread postPosted: Fri Jun 28, 2013 6:13 pm
by Ted Smith
More photos!
037.JPG
Jim Hickman has just finished covering a window with a shutter to discourage theft of parts and tools stored inside. Clyde Putman uses this equipment for maintenance of wheels, brakes and safety appliances.
039.JPG
New siding has been installed on the end of the hoist house of Derrick OP.
040.JPG
This photo shows progress on Derrick OP, as of the end of Work Session D. Grab irons have been installed, along with a temporary door.
041 - 301.00 Terry Woolsey & Mike Mahoney & Paul Davenport JG-i_F_7777 resize 705ppi.jpg
The Maintenance-of- Way Team does not get the credit they deserve! Sometimes they walk miles to get to their work sites. MOW Team Leader Jim Gross was kind enough to provide this photo, as well as those that follow, of the work they accomplished in Session C. Paul Davenport is in the background, cutting brush; Mike Mahoney and Paul Davenport are also in the photo.
041 - 301.00 Terry Woolsey & Mike Mahoney & Paul Davenport JG-i_F_7777 resize 705ppi.jpg (515.65 KiB) Viewed 2431 times
042 - 302.00  Terry Woolsey & Mike Mahoney PD-IMG_0355 resize 705ppi.jpg
Terry Woolsey and Mike Mahoney paint Mile Post 302.
042 - 302.00 Terry Woolsey & Mike Mahoney PD-IMG_0355 resize 705ppi.jpg (490.23 KiB) Viewed 2431 times
043 - 319.95 John Mitchell & Paul Davenport MM-DSC_2345 resize 470ppi.jpg
John Mitchell and Paul Davenport are shown here after hiking three and five miles, respectively, to paint Mile Post 321 and Mile Post 322.
043 - 319.95 John Mitchell & Paul Davenport MM-DSC_2345 resize 470ppi.jpg (407.19 KiB) Viewed 2431 times
044 - 319.95 Mike Mahoney PD-IMG_0323 resize 705ppi.jpg
Mike Mahoney measures the bridge number board for the east end of Cascade Trestle. Terry Woolsey is in the background.
044 - 319.95 Mike Mahoney PD-IMG_0323 resize 705ppi.jpg (587.78 KiB) Viewed 2431 times
045 - 319.95 Mike Mahoney PD-IMG_0324 resize 705ppi.jpg
Mike Mahoney is shown on the east end of Cascade Trestle, figuring out how to put the bridge number board on the west end before walking the trestle.
045 - 319.95 Mike Mahoney PD-IMG_0324 resize 705ppi.jpg (625.26 KiB) Viewed 2431 times

Re: WORK SESSION D - Friday, July 28, 2013 - Part II

Unread postPosted: Fri Jun 28, 2013 9:09 pm
by Blake Bogs
Great job as always!
Enjoy
Blake

Re: WORK SESSION D - Friday, July 28, 2013 - Part II

Unread postPosted: Sat Jun 29, 2013 12:00 pm
by Jason Rose
One of these years I plan to be on the MOW team.

Thanks for the photos!