Wednesday 7/26/17 Emuse

Discussion Pertaining to Work Session E - 2017

Wednesday 7/26/17 Emuse

Unread postby Sharon Evans » Wed Jul 26, 2017 2:37 pm

Well no rain today to spoil the activities going on. Sunny with cloudy periods and temperatures upper 70's for the most part. The most interesting thing going on today was the placing of the air tank into the sand house. The Friends have been working most of the summer sessions repairing the sand house getting it ready to provide sand to the locomotives on a daily basis. Next step, which should happen tomorrow is raising the storage tank for the sand onto the tower from which gravity will allow locomotive crews to fill the sand dome. Keep in mind that this air tank weighs around 800 lbs.
7-26-17 Barry Morris installs the comealong support for moving the air tank into place.jpg
Barry Morris, part of the crew working on the sand house, installs the chains to support the come-along that will be used to raise the tank

7-26-17 Using a fork lift, they move the 800 lb air tank to the boards they will roll it on.jpg
Using a bucket loader with folk attachments and a sling, then get to moving the tank toward the board that will be used to roll it to the sand house

7-26-17 Almost to the boards.jpg
The crew has almost gotten the tank to the board

7-26-17 Rolling it toward the sand house.jpg
The crew now man handles the tank along the boards

7-26-17 The tank is now starting to tip into the pit.jpg
They now have the tank starting to tip over into the pit where it will reside

7-26-17 The comealong is now attached directly to the tank.jpg
The crew has moved the tank far enough to attach the come-along directly to the top of the tank

7-26-17 The air tank is now being lowered into the pit_.jpg
Lowering is begining

7-26-17 Before the tank is lowered the last few inches a plumb bob was lowered from the roof through the pipe hole so the tank could be centered.jpg
Before the tank is lowered the final few inches, a plumb bob was lowered through the hole in the roof where the air pipe needs to go to ensure alignment
Last edited by Sharon Evans on Wed Jul 26, 2017 3:20 pm, edited 9 times in total.
Sharon Evans
Conductor
Conductor
 
Posts: 4886
Joined: Tue Oct 21, 2014 2:54 pm
Location: Glen Allen, VA

Re: Wednesday 7/26/17

Unread postby Rich Murray » Wed Jul 26, 2017 2:39 pm

Thank you Sharon. I've been wondering how that project was progressing.
User avatar
Rich Murray
Moderator
Moderator
 
Posts: 1048
Joined: Thu Nov 17, 2011 3:30 pm

Re: Wednesday 7/26/17

Unread postby Sharon Evans » Wed Jul 26, 2017 2:46 pm

Check back, I am still adding photos.
Sharon Evans
Conductor
Conductor
 
Posts: 4886
Joined: Tue Oct 21, 2014 2:54 pm
Location: Glen Allen, VA

Re: Wednesday 7/26/17 Emuse

Unread postby John Cole » Sat Jul 29, 2017 10:00 pm

Years ago when the Friends were working on that tank, the reason the pipe was clogged up was because there was a rat that somehow got inside the pipe and died, when they applied pressure it shot out the pipe to the sand hopper on the tower. For awhile it was known as the 'rat-a-pault'.
John Cole
Conductor
Conductor
 
Posts: 729
Joined: Mon Nov 28, 2011 12:55 pm

Re: Wednesday 7/26/17 Emuse

Unread postby Rich Murray » Sun Jul 30, 2017 7:04 am

Sharon, did the storage tank get installed and if do do we know when the system will be tested?
User avatar
Rich Murray
Moderator
Moderator
 
Posts: 1048
Joined: Thu Nov 17, 2011 3:30 pm

Re: Wednesday 7/26/17 Emuse

Unread postby Sharon Evans » Sun Jul 30, 2017 6:58 pm

Rich, the current plan calls for it to be raised tomorrow. If I am in Chama will be shooting video of the event.
Sharon Evans
Conductor
Conductor
 
Posts: 4886
Joined: Tue Oct 21, 2014 2:54 pm
Location: Glen Allen, VA

Re: Wednesday 7/26/17 Emuse

Unread postby Craig Kumler » Sun Jul 30, 2017 8:09 pm

I hope you make it Sharon as I look forward to all your fine pics daily!
Craig Kumler
Engineer
Engineer
 
Posts: 392
Joined: Mon Nov 28, 2011 4:24 pm
Location: San Jose, Ca.

Re: Wednesday 7/26/17 Emuse

Unread postby Rich Murray » Mon Jul 31, 2017 7:28 am

Sharon Evans wrote:Rich, the current plan calls for it to be raised tomorrow. If I am in Chama will be shooting video of the event.


Thank you Sharon!
I will be looking forward to the Video.
User avatar
Rich Murray
Moderator
Moderator
 
Posts: 1048
Joined: Thu Nov 17, 2011 3:30 pm

Re: Wednesday 7/26/17 Emuse

Unread postby Sharon Evans » Tue Aug 01, 2017 6:29 pm

Now the conversion of the p box to box car 3537 for Wednesday.
2017.1294.pbox202-boxcar3537.0726.013.see.jpg
The newly constructed door for the left side of the car is almost ready to install. The MOW bunk car can be seen in the background.

2017.1294.pbox202-boxcar3537.0726.015.see.jpg
The full crew of the 3537 is man handling the door up onto the track as Dr. McMullen from the bunk car acts as spotted

2017.1294.pbox202-boxcar3537.0726.017.see.jpg
The door is on and Don Bayer is checking to see how freely is rolls

2017.1294.pbox202-boxcar3537.0726.018.see.jpg
Shot of the left side of the 3537 with the door on and closed


Moving across the tracks to the bunk car.
2017.1295.04258.0726.015.see.jpg
The windows have been attached to the car. Unbeknown to the crew they would have to remove them for the car to be painted

2017.1295.04258.0726.021.see.jpg
This shot shows the hardware for the roof step before the wood is attached, and no I did not climb up there for these shots

2017.1295.04258.0726.022.see.jpg
The after shot with the boards attached

2017.1295.04258.0726.026.see.jpg
This is the metal heat shield be attached to the wall before the stove was placed into the car
Sharon Evans
Conductor
Conductor
 
Posts: 4886
Joined: Tue Oct 21, 2014 2:54 pm
Location: Glen Allen, VA


Return to Work Session E (July 24-28)

Who is online

Users browsing this forum: No registered users and 1 guest